16 tasks and 23 bugs commited for the next sprint of maemo.org development
0
0
The second maemo.org development IRC meeting concluded last Tuesday with 16 tasks committed for the Sprint3, from which 9 were carried from the previous sprint. There are currently 23 bugs with high priority that are being tried to be resolved by Tuesday 2008/08/12, end of the current sprint.
This is the third of five sprints comprising the 100 days Action Plan and most tasks are open to contributions from community members. See How to push a maemo.org task.
Sprint 2 Review
Committed | Task | Owner | % | Highlights |
---|---|---|---|---|
2008-05-10 | Who's who in Maemo | Dave | % | Discussion on implementation details pending |
2008-05-10 | Companies in Maemo development | Dave | 60% | Initial group of companies defined, need logos & descriptions, and have list checked |
2008-06-10 | Consolidation of Extras | Niels | 0% | Niels must specify what goes in this sprint |
2008-06-10 | Extras % maemo.org/downloads integration | Niels | % | Complete and/or document in wiki page |
2006-06-10 | Registration and sponsorship for Maemo summit 2008 | Oskari/Bergie | 90% | Working, some bugs left |
2008-06-10 | Update maemo.org/intro | Dave | DONE | Just few pages waiting to be moved - links to be added |
2008-06-10 | Better extras categories and debtags | Niels | % | Proposal needs to be drafted in wiki page |
2008-06-10 | Put the Bugsquad in place | Andre/Karsten | 40% | See this mail - Done: Triage guide in place |
2008-06-10 | Forum interface to mailing lists released | Oskari/Bergie | % | Beta to be made public for testing |
2008-06-10 | User profile improvements defined and started | Oskari/Bergie | 70% | Revamped, some bugs left |
2008-06-10 | No pages remaining in Category:Midgard wiki | Dave | 20% | Decided to discontinue this task |
2008-06-30 | Maemo brand | Quim | DONE | Considering this OK. Formal approval before the next sprint meeting unless someone finds a bug. |
2008-06-30 | Sprint progress | Quim | DONE | The process is setup, now it's up to everybody to do their part. |
2008-06-30 | Components and packages | Soumya | DONE | Table ready, problems uploading |
2008-06-30 | Maemo.org_logo_contest selection process | Dave | % | Agreed that needs to be selection and not voting |
2008-06-30 | Maemo Summit 2008 organization | Quim | DONE | In sync with c-base and all tasks listed - objectives of the sprint completed |
2008-06-30 | All components of product Website in good hands | Andre | DONE | All bugs triaged, missing only component owners list in this wiki |
Sprint 3 Plan
Committed | Task | Owner | % | Highlights |
---|---|---|---|---|
2008-05-10 | Who's who in Maemo | Dave | 0% | Discussion on implementation details pending |
2008-05-10 | Companies in Maemo development | Dave | 60% | Initial group of companies defined, need logos & descriptions, and have list checked |
2008-06-10 | Extras & maemo.org/downloads integration | Niels | 0% | Complete and/or document in wiki page |
2006-06-10 | Registration and sponsorship for Maemo summit 2008 | Oskari/Bergie | 90% | Working, some bugs left |
2008-06-10 | Better extras categories and debtags | Niels | 0% | Proposal needs to be drafted in wiki page |
2008-06-10 | Put the Bugsquad in place | Andre/Karsten | 40% | See this mail - Done: Triage guide in place |
2008-06-10 | Forum interface to mailing lists released | Oskari/Bergie | 0% | Beta to be made public for testing |
2008-06-10 | User profile improvements defined and started | Oskari/Bergie | 70% | Revamped, some bugs left |
2008-06-30 | Get a Maemo.org_logo_contest winner | Dave | 0% | Agreed that needs to be selection and not voting |
2008-07-22 | Task:Remarkable community projects around Maemo | Dave | 0% | |
2008-07-22 | Task:Upstream projects Maemo relies upon | Dave | 0% | |
2008-07-22 | Complete the 2010 Agenda community proposal | Quim | 10% | Started with Objective:Release_soon_and_often |
2008-07-22 | Task:Using garage.maemo.org | Ferenc | 0% | |
2008-07-22 | Maemo Summit infrastructure defined | Quim | 25% | Broad agreement with c-base, waiting their proposal |
2008-07-22 | Summit sponsored participants decided | Quim | 50% | A bunch approved, waiting for costs to know how much budget left for more |
2008-07-22 | Maemo community in OSiM | Quim | 0% |